LuxuryDade tracks 91 South Florida condo and mixed-use projects that carry a dated published source, and only 34 of them have cleared permitting, while the 73 that publish a unit count add up to 31,038 units. Those 34 permitted projects now hold 41.2 percent of the units, down from 57.5 percent three weeks ago, because almost every project added since has been paper. Ask a sales agent which stage a tower is in before you ask its price.

Every week a buyer sends me a rendering and asks what I think of the building. The rendering never says whether anyone has pulled a permit. It does not say whether a site plan has been filed, whether the land is even under contract, or whether the whole thing is a press release attached to an architect's name. That gap between what a project looks like and where it actually stands is the single most expensive thing a pre-construction buyer does not know.
So I keep a file. This report opens it. It is a stage-by-stage census of the 91 South Florida condominium and mixed-use development projects I track that carry at least one dated published source, current to September 26, 2026. Every project is listed by name further down with its stage and the dated report that assignment rests on, so you can check any single row without asking me. It answers one question in one place: of everything being announced across Miami-Dade, Broward and Palm Beach, how much of it is real right now.
What Changed This Month: September 2026
This is the monthly update. Every event below is dated, comes from our development tracking file, and links to the original report and to our own page for the project. It covers September 1 to September 30, 2026, read on October 1, 2026. Sixteen residential tower events moved this month; nine of them are announcements, filings, proposals or approvals, which is the paper side of the census below.
Sales launched
- Sept. 1, 2026. WOMA Wynwood launched sales: Uribe Schwarzkopf opened the 163-unit condo at Northwest 5th Avenue and Northwest 32nd Street, priced from $380,000 to $1.2 million. Source: The Real Deal. See our page.
Construction milestones
- Sept. 2, 2026. Foundation work is underway at 7200 Collins, a 12-story, 222-unit condominium in North Beach, Miami Beach. Source: Florida YIMBY. See our page.
- Sept. 14, 2026. The Rider Residences topped off: the 12-story, 152-residence building at 94 NE 29th St is 50 percent sold, with completion expected in the second half of 2027. Source: PROFILEmiami. See our tracker.
- Sept. 24, 2026. Parkside Residences Brickell reached its second-floor construction milestone, with pricing starting in the $400,000s. Source: PROFILEmiami. See our tracker.
- Sept. 29, 2026. Completion was announced at Nexo Residences, the 254-residence building at 13899 Biscayne Boulevard in North Miami Beach, with more than 90 percent of the residences sold to buyers from more than 25 countries. Source: Florida YIMBY. See our page.
Construction financing closed
- Sept. 1, 2026. Shoma Group secured a $172.5 million construction loan for its 24-story, 333-unit condo tower at 1850 John F. Kennedy Causeway in North Bay Village. Source: The Real Deal. See our tracker.
- Sept. 25, 2026. Bank OZK provided a $259 million construction loan to Fortune International Group and Oak Capital for The Ritz-Carlton Residences, West Palm Beach. Source: Bisnow. See our tracker.
Announced or reshaped
- Sept. 4, 2026. Fort Partners joined the BH3 and Merrimac joint venture on Watson Harbour, a hotel, condominium, retail and office project on Watson Island. Source: The Real Deal. See our tracker.
- Sept. 16, 2026. Bugatti Residences Miami was officially revealed: a 60-story tower with 183 residences at 75 SW Miami Avenue Road, with sales slated to launch in the first half of 2027. Source: PROFILEmiami. See our page.
New filings, proposals and approvals
- Sept. 1, 2026. Urbania Development is planning a 28-story tower with 70 residences at 7915 East Drive in North Bay Village. Source: Florida YIMBY. See our tracker.
- Sept. 16, 2026. Allied Partners plans a 38-story tower on the Savoy Hotel site at 425 Ocean Drive with a hotel, 90 condo units and 60 workforce rental apartments. Source: The Real Deal. See our tracker.
- Sept. 20, 2026. Developers filed plans under the Live Local Act to restore the 1939 Bancroft Hotel at 1501 Collins Avenue and build a 25-story tower with 124 residences and 42 hotel rooms. Source: Florida YIMBY. See our tracker.
- Sept. 20, 2026. El-Ad Properties filed a two-tower plan on East Drive whose 46-story, 518-foot tower would be the tallest ever built in North Bay Village. Source: Markets of Tomorrow. See our tracker.
- Sept. 21, 2026. Crescent Heights filed for administrative approval of a 43-story tower with 163 residences at 1575 Alton Road, up from an earlier 18-story, 92-unit plan. Source: Florida YIMBY. See our tracker.
- Sept. 28, 2026. The Weston City Commission approved H&M Development's plan for 132 for-sale condominiums in eleven four-story buildings at 357 Racquet Club Road. Source: The Real Deal. See our page.
- Sept. 28, 2026. Turnbridge Equities plans Reserve at One Sunset, a 20-story Miami Beach tower with 35 units, 21 of them three to five-bedroom condos and 14 workforce homes, through the Live Local Act. Source: Florida YIMBY. See our tracker.
My read on September: the money moved to projects already in the ground. Two construction loans and four construction milestones landed on permitted projects, the last of them Nexo Residences finishing at more than 90 percent sold, while the two headline launches, WOMA Wynwood and Bugatti Residences Miami, had not cleared permitting in our file. That is the pattern I tell buyers to watch before a deposit: price the stage first, then the unit.
- What Changed This Month: September 2026
- The Stage Census: Where 91 Projects Actually Stand
- Only 37 Percent Have Cleared Permitting, and the Paper Side Now Holds More Units
- The 31,038 Units the Inventory Reports Cannot See
- Miami-Dade Carries 64 of 91, and Broward Builds the Biggest
- What Each Stage Means, and What Skipping the Question Costs
- Where the Reporting Comes From: 129 Dated Citations
- The Full Register: Every Project, Its Stage and the Dated Report Behind It
- Gerardo's Read: I Price the Stage Before I Price the Unit
- Methodology, Scope and What This Cannot Tell You
- Frequently Asked Questions
The Stage Census: Where 91 Projects Actually Stand
A development does not go from announcement to keys in one step. It moves through stages, each one a public act that costs the developer real money and creates a real record. Sorting the tracked set by stage is the fastest way to see how much of the noise is signal.
| Stage | Projects | Share | Publishing Units | Units |
|---|---|---|---|---|
| Rumor | 4 | 4.4% | 1 | 829 |
| Proposed | 15 | 16.5% | 13 | 2,846 |
| Filed | 15 | 16.5% | 13 | 7,387 |
| Planned | 20 | 22.0% | 15 | 6,985 |
| Permitted | 15 | 16.5% | 11 | 6,409 |
| Under construction | 16 | 17.6% | 14 | 5,770 |
| Coming soon | 3 | 3.3% | 3 | 199 |
| Completed | 3 | 3.3% | 3 | 613 |
| Total | 91 | 100% | 73 | 31,038 |
The single largest stage is planned, with 20 projects. Planned means a design exists and the developer is talking about it publicly, but the building permit is not issued. Add rumor, proposed and filed and 54 of the 91 projects, 59.3 percent, are somewhere in that pre-permit territory where the unit count on the brochure is a proposal rather than a fact. Filed is the stage that grew fastest, from nine projects and 1,869 units on September 5 to 15 projects and 7,387 units now.

Only 37 Percent Have Cleared Permitting, and the Paper Side Now Holds More Units
Group the eight stages into three buckets and the shape of the pipeline changes. Permitted, under construction and completed are the projects that have cleared the legal hurdle to rise. Rumor, proposed, filed and planned are still paper. Coming soon sits between them, marketing a launch without a permit behind it.
| Bucket | Projects | Share of Projects | Units | Share of Units |
|---|---|---|---|---|
| Past permitting | 34 | 37.4% | 12,792 | 41.2% |
| Still on paper | 54 | 59.3% | 18,047 | 58.1% |
| Coming soon, no permit | 3 | 3.3% | 199 | 0.6% |
That is a reversal from the September 5 edition of this report, and it is the finding of this one. Three weeks ago 29 permitted projects held 57.5 percent of the tracked units while 43 paper projects held 41.7 percent. Today 34 permitted projects hold 41.2 percent and 54 paper projects hold 58.1 percent. Nothing moved backwards and no project lost a permit. The file absorbed 21 new projects between September 5 and September 26, 15 of them still on paper, and two of those filed projects carry more than 700 units each.
The old logic still holds inside each bucket. Reaching a permit in South Florida takes years of carrying cost, consultants and a lender who has looked at the numbers, so the average past-permitting project is still slightly larger at 457 published units against 430 on the paper side. What changed is the balance between the buckets. The announcement side of this market is now growing faster than the permitted side, which is exactly the condition in which a brochure unit count is most likely to be revised.
For a buyer the practical translation is short. Most of the units being talked about in South Florida right now sit behind a permit that has not been issued. The supply that will genuinely compete with your resale in three years is the 12,792 units already cleared to rise, not the 31,038 in the headlines.
People assume the risk in pre-construction is that the market turns. In my experience the more common outcome is quieter than that: the project never gets built, the deposit comes back years later, and the buyer has lost the appreciation they would have earned somewhere real.
Gerardo Gonzalez, Licensed Real Estate Agent at Compass

The 31,038 Units the Inventory Reports Cannot See
Every month somebody quotes a months-of-supply number at me as if it settles the question of whether South Florida is oversupplied. It does not, and the reason is printed in the source itself. MIAMI REALTORS states in every release that its sales totals do not include South Florida new construction, pre-construction or condo conversion sales, because they are largely not reported in the MLS (MIAMI REALTORS + RWorld, August 2026).
So the monthly numbers measure the resale market, and they measure it well. Here is what they say, alongside the pipeline they cannot see.
| County | Resale Months of Supply | Active Resale Listings | Tracked Pipeline Projects | Tracked Pipeline Units |
|---|---|---|---|---|
| Miami-Dade | 12.1 | 11,495 | 64 | 20,322 |
| Broward | 9.9 | 9,427 | 14 | 8,210 |
| Palm Beach | 6.7 | 5,770 | 13 | 2,506 |
Miami-Dade resale condo inventory fell 9.04 percent year over year in August 2026, from 12,637 active listings to 11,495, a seventh straight monthly decline (MIAMI REALTORS + RWorld). Broward condo inventory fell 14.84 percent to 9,427 listings (MIAMI REALTORS + RWorld) and Palm Beach fell 17.09 percent to 5,770 (MIAMI REALTORS + RWorld).
Read those two facts together and the market looks different from either one alone. Resale supply is tightening across all three counties for the seventh straight month, while a pipeline of 31,038 tracked units waits behind it, most of it still unpermitted. Neither number is wrong. They just describe different halves of the same market, and only one of them gets published every month.
Miami-Dade Carries 64 of 91, and Broward Builds the Biggest
Concentration matters more than the headline count. Miami-Dade holds 64 of the 91 tracked projects, 70.3 percent of the file, and 25 of those have cleared permitting. I map the major Miami-Dade projects by area in a separate guide. Broward and Palm Beach are far smaller by project count but they are not smaller by ambition.
| County | Projects | Past Permitting | Share Past Permitting | Units Published | Average Project |
|---|---|---|---|---|---|
| Miami-Dade | 64 | 25 | 39.1% | 20,322 | 391 units |
| Broward | 14 | 5 | 35.7% | 8,210 | 746 units |
| Palm Beach | 13 | 4 | 30.8% | 2,506 | 251 units |
Broward averages 746 units per project, nearly twice Miami-Dade's 391 and almost three times Palm Beach's 251. Land parcels north of the county line are bigger and cheaper, so the projects that pencil there are large multi-tower schemes rather than single boutique buildings. Palm Beach runs the opposite way, with the smallest average project and the lowest permitted share of the three. Broward also gained the single largest addition of the last three weeks, The Plaza Davie District at 1,292 units, which is already under construction.

What Each Stage Means, and What Skipping the Question Costs
Stage language gets used loosely in sales galleries. Here is what each term means in practice, and what it tells you about the odds.
| Stage | What Has Actually Happened | Projects |
|---|---|---|
| Rumor | Reported interest, a land tour or a broker whisper. Nothing filed, nothing confirmed by the owner. | 4 |
| Proposed | The developer has announced an intent publicly. Design can still change completely. | 15 |
| Filed | A public application exists with a city or county board. No approval yet. | 15 |
| Planned | Approved or advancing with a published design and unit count, but no building permit. | 20 |
| Permitted | The building permit is issued. The project is legally cleared to rise. | 15 |
| Under construction | Work is visibly underway on site, from piles to topping out. | 16 |
| Coming soon | Sales are being marketed ahead of a permit. Timeline is a target, not a schedule. | 3 |
| Completed | Delivered. Any remaining units are developer inventory, not pre-construction. | 3 |
- Rumor and proposed: treat the unit count, the price and the delivery year as placeholders. All three routinely move.
- Filed and planned: the design is real enough to evaluate, but a deposit here is funding a project that still needs a permit to exist.
- Permitted: the first stage where the marketed timeline is worth taking seriously. Ask for the permit number.
- Under construction: the risk shifts from whether it happens to when. Delays are normal, cancellation is rare.

Where the Reporting Comes From: 129 Dated Citations
A pipeline file is only as good as what it is built from. Every one of the 91 projects here carries at least one dated report from a named publication or a developer's own site, 129 citations in total, and 123 of those 129 were published in 2026. The newest is dated September 23, 2026.
| Publication | Dated Citations | Share |
|---|---|---|
| Florida YIMBY | 54 | 41.9% |
| The Real Deal | 45 | 34.9% |
| South Florida Business Journal | 7 | 5.4% |
| PROFILEmiami | 5 | 3.9% |
| Bisnow | 4 | 3.1% |
| Other outlets and developer sites | 14 | 10.9% |
Two outlets, The Real Deal and Florida YIMBY, account for 76.7 percent of the citations. That is a real limitation and worth stating plainly: this file inherits their coverage priorities. A project that never gets written up does not appear here, no matter how far along it is. For wider context on regional volume, Bisnow has put roughly 115 condo projects and nearly 18,000 units in preconstruction across the Downtown Miami core, Miami Beach and Broward.
The Full Register: Every Project, Its Stage and the Dated Report Behind It
A stage count is only worth citing if someone can check it. So here is the whole file, one row per project, sorted from rumor through completed. Each row names the project, the stage I have assigned it, the county, the unit count the developer or the reporting outlet published, and the date and publication of the most recent report that the stage assignment rests on. Click the date to open the source.
If a row looks wrong to you, it is checkable in one click, which is the point. The same table is published as a downloadable CSV with two extra columns, the neighborhood and the date the project first entered the file, so you can reproduce every figure on this page yourself.
| Project | Stage | County | Units | Latest dated source |
|---|---|---|---|---|
| Blue Lagoon development site (near Miami International Airport) | Rumor | Miami-Dade | 829 | 2026-08-18, South Florida Business Journal |
| Mana Wynwood Complex | Rumor | Miami-Dade | not published | 2026-08-27, The Real Deal |
| OKO Group Edgewater waterfront tower (next to Missoni Baia) | Rumor | Miami-Dade | not published | 2026-06-19, The Real Deal |
| St. Regis-branded condominium (2023 North Flagler Drive) | Rumor | Palm Beach | not published | 2026-09-01, Boca Raton Tribune (Palm Beach Post) |
| 1501 Collins Avenue (Bancroft Hotel) | Proposed | Miami-Dade | 124 | 2026-09-20, Florida YIMBY |
| 534 Datura Street Live Local tower | Proposed | Palm Beach | 261 | 2026-09-11, Florida YIMBY |
| 7931 East Drive | Proposed | Miami-Dade | 165 | 2026-09-20, Markets of Tomorrow |
| Culmer Gardens on 5th | Proposed | Miami-Dade | 250 | 2026-08-12, Florida YIMBY |
| Deerfield Beach City Center | Proposed | Broward | 150 | 2026-09-08, Florida YIMBY |
| Gateway 2 | Proposed | Miami-Dade | 376 | 2026-08-02, Florida YIMBY |
| Opa-locka Downtown Redevelopment | Proposed | Miami-Dade | not published | 2026-08-06, The Real Deal |
| Raleigh Miami Beach expansion (Nahla Capital) | Proposed | Miami-Dade | not published | 2026-07-07, The Real Deal |
| Rio Vista Residences | Proposed | Broward | 440 | 2026-09-14, The Real Deal |
| Savoy Hotel site tower (425 Ocean Drive) | Proposed | Miami-Dade | 90 | 2026-09-16, The Real Deal |
| Sunrise Arena District (Amerant Bank Arena redevelopment) | Proposed | Broward | 154 | 2026-08-10, The Real Deal |
| Terra / BH Group Two 31-Story Condo Towers (2085 N Flagler Dr) | Proposed | Palm Beach | 281 | 2026-06-18, Florida YIMBY |
| The Cypress at 400 Corporate Drive | Proposed | Broward | 340 | 2026-08-30, South Florida Business Journal |
| Turnberry Isle Condo Towers | Proposed | Miami-Dade | 145 | 2026-08-10, Bisnow |
| Urbania Development 28-Story Tower (7915 East Drive) | Proposed | Miami-Dade | 70 | 2026-09-01, Florida YIMBY |
| 13th Edge (Grupo T&C, near Brickell Metromover) | Filed | Miami-Dade | 400 | 2026-06-15, Florida YIMBY |
| 1575 Alton Road (Crescent Heights, historic Firestone site) | Filed | Miami-Dade | 163 | 2026-09-21, The Real Deal |
| 215 Fifth Street | Filed | Palm Beach | 41 | 2026-08-26, The Real Deal |
| 220 Congress Park Drive residential project | Filed | Palm Beach | not published | 2026-09-23, Florida YIMBY |
| 3180 Biscayne Boulevard two-tower project | Filed | Miami-Dade | 1,030 | 2026-09-23, Miami Today |
| 464 Fern Street Residences | Filed | Palm Beach | 194 | 2026-08-21, Florida YIMBY |
| Annie Coleman Redevelopment | Filed | Miami-Dade | 180 | 2026-08-24, Florida YIMBY |
| Li'l Abner IV | Filed | Miami-Dade | 250 | 2026-08-10, Florida YIMBY |
| Magnus Grove (Stirrup Plaza redevelopment) | Filed | Miami-Dade | not published | 2026-08-02, South Florida Business Journal |
| Miami World Towers Phase 2B (20 NE 8th Street) | Filed | Miami-Dade | 705 | 2026-05-24, Florida YIMBY |
| Nine Hundred | Filed | Broward | 540 | 2026-08-30, Florida YIMBY |
| Northside Town Station II | Filed | Miami-Dade | 280 | 2026-08-09, Florida YIMBY |
| Ohio Allapattah | Filed | Miami-Dade | 260 | 2026-09-12, Florida YIMBY |
| Solara Village | Filed | Miami-Dade | 200 | 2026-08-17, Florida YIMBY |
| The Galleria at Fort Lauderdale Redevelopment | Filed | Broward | 3,144 | 2026-09-05, South Florida Sun Sentinel |
| 1250 West Avenue (Bay Garden Manor redevelopment) | Planned | Miami-Dade | 106 | 2026-08-03, The Real Deal |
| 7410 Collins Avenue | Planned | Miami-Dade | 50 | 2026-09-06, Florida YIMBY |
| Aurevia | Planned | Miami-Dade | 225 | 2026-09-13, Florida YIMBY |
| Aventura City Center (BH Group + Apollo Cos) | Planned | Miami-Dade | not published | 2026-07-07, The Real Deal |
| B Residences Miami (Breitling-branded) | Planned | Miami-Dade | 300 | 2026-06-27, Florida YIMBY |
| Beach House by Turnberry at SoLe Mia | Planned | Miami-Dade | 515 | 2026-08-20, The Real Deal |
| Downtown SoMi (Shops at Sunset Place redevelopment) | Planned | Miami-Dade | 1,513 | 2026-07-15, The Real Deal |
| EnSima Miami Gardens | Planned | Miami-Dade | 670 | 2026-07-30, The Real Deal |
| Eurus at Kendall | Planned | Miami-Dade | not published | 2026-07-09, Florida YIMBY |
| La Fontana co-op redevelopment (Chuck Whittall) | Planned | Palm Beach | not published | 2026-09-01, Boca Raton Tribune (Palm Beach Post) |
| Lakeview at Naranja | Planned | Miami-Dade | 328 | 2026-09-09, Florida YIMBY |
| Magic City Innovation District | Planned | Miami-Dade | not published | 2026-06, Florida YIMBY |
| Magnolia Point Phase 1 | Planned | Miami-Dade | 409 | 2026-09-12, Florida YIMBY |
| Metropica | Planned | Broward | 1,300 | 2026-08-31, The Real Deal |
| Redland Reserve | Planned | Miami-Dade | 582 | 2026-09-08, The Real Deal |
| Shoppes at Wilton Manors Redevelopment | Planned | Broward | 89 | 2026-08-27, The Real Deal |
| The Ritz-Carlton Residences, Fort Lauderdale Beach | Planned | Broward | not published | 2026-07-08, Florida YIMBY |
| The Sutton | Planned | Palm Beach | 432 | 2026-07-15, Florida YIMBY |
| Vybe 75 | Planned | Miami-Dade | 366 | 2026-08-11, Florida YIMBY |
| Watson Harbour | Planned | Miami-Dade | 100 | 2026-09-04, The Real Deal |
| 3333 Biscayne Boulevard | Permitted | Miami-Dade | 667 | 2026-08-10, Florida YIMBY |
| 700 North Miami Avenue at Miami Worldcenter | Permitted | Miami-Dade | 2,346 | 2026-07-27, PROFILEmiami |
| Alton Biscayne | Permitted | Miami-Dade | 336 | 2026-08-13, The Real Deal |
| Billionaires' Beach (100 Lincoln Road) | Permitted | Miami-Dade | 30 | 2026-07-20, The Real Deal |
| Biscayne 18 | Permitted | Miami-Dade | 1,178 | 2026-07-26, Florida YIMBY |
| Crystal Residences | Permitted | Miami-Dade | 184 | 2026-08-27, The Real Deal |
| Forma Suites Phase 2 | Permitted | Miami-Dade | not published | 2026-08-20, The Real Deal |
| Gallery at Lummus | Permitted | Miami-Dade | 440 | 2026-08-06, The Real Deal |
| Mohawk at Wynwood | Permitted | Miami-Dade | 300 | 2026-08-13, The Real Deal |
| NoMi Botanik (Project Land) | Permitted | Miami-Dade | 48 | 2026-06-20, Florida YIMBY |
| ODA-Designed Skyscrapers (Fort Lauderdale) | Permitted | Broward | not published | 2026-07-10, Florida YIMBY |
| Rybovich Marina Redevelopment | Permitted | Palm Beach | 660 | 2025-09-18, The Real Deal |
| The Opus at 701 (Fort Lauderdale) | Permitted | Broward | not published | 2026-06-19, South Florida Agent |
| The Ritz-Carlton, South Beach (1 Lincoln Road) | Permitted | Miami-Dade | not published | 2026-07-30, The Real Deal |
| The Winsberg at Green Cay | Permitted | Palm Beach | 220 | 2026-09-07, Florida YIMBY |
| 1775 Biscayne (LCOR) | Under construction | Miami-Dade | 544 | 2026-07-04, Florida YIMBY |
| 2900 Terrace | Under construction | Miami-Dade | 324 | 2026-08-31, Florida YIMBY |
| Aventana | Under construction | Miami-Dade | 334 | 2026-09-13, Florida YIMBY |
| Crescendo at Link at Douglas | Under construction | Miami-Dade | 392 | 2026-07-22, South Florida Agent |
| La Baia South | Under construction | Miami-Dade | not published | 2026-08-04, The Real Deal |
| Le Parc Lauderhill | Under construction | Broward | 385 | 2026-08-11, Florida YIMBY |
| One Brickell Riverfront (LOFTY Brickell + The Standard Residences Brickell) | Under construction | Miami-Dade | 784 | 2026-08-05, The Real Deal |
| Prime Square Doral | Under construction | Miami-Dade | not published | 2026-09, Florida YIMBY |
| Serenity Gardens | Under construction | Miami-Dade | 153 | 2026-08-10, Bisnow |
| Shoma Bay | Under construction | Miami-Dade | 333 | 2026-09-01, The Real Deal |
| The Aurelian | Under construction | Miami-Dade | 161 | 2026-08-13, Florida YIMBY |
| The Cove (1055 N Federal Highway) | Under construction | Broward | 376 | 2026-08-03, Bisnow |
| The Plaza Davie District | Under construction | Broward | 1,292 | 2026-09-10, Florida YIMBY |
| The Residences at Claude Pepper | Under construction | Miami-Dade | 428 | 2026-06-28, Florida YIMBY |
| The Rider Residences | Under construction | Miami-Dade | 152 | 2026-09-14, PROFILEmiami |
| The Triangle | Under construction | Miami-Dade | 112 | 2026-09-05, Florida YIMBY |
| Lumara Residences | Coming soon | Miami-Dade | 139 | 2026-08-20, The Real Deal |
| Midtown Park Residences by Proper | Coming soon | Miami-Dade | 28 | 2026-07-15, The Real Deal |
| OLIN Palm Beach | Coming soon | Palm Beach | 32 | 2026-08-02, OLIN Palm Beach (developer site) |
| Alba Palm Beach | Completed | Palm Beach | 55 | 2026-06-25, PROFILEmiami |
| Nautilus 220 | Completed | Palm Beach | 330 | 2026-08-11, Developer site |
| The Standard Residences, Midtown Miami | Completed | Miami-Dade | 228 | 2026-06-21, Florida YIMBY |
Eighteen of the 91 rows carry no unit count. That is not an omission on my side: those developers have published no unit figure, so the honest cell is blank rather than an estimate. It also means the real pipeline is larger than 31,038 units, not smaller.
Gerardo's Read: I Price the Stage Before I Price the Unit
The advice I give buyers on pre-construction has narrowed to one question over the last two years, and it is not about the finishes. It is whether anyone has pulled a permit. Everything else on the table, the price per foot, the deposit schedule, the amenity list, is a negotiation. The permit is a fact.
What I tell clients weighing an early-stage tower against a permitted one is this. At planned stage you are being asked to fund optionality. You take the launch pricing, and in exchange you accept that the building may be redesigned, resized, delayed by years, or never built at all, and that your money sits in escrow while the market moves without you. That trade can be worth it, but only when the discount to a permitted comparable is large enough to pay you for the wait. Most of the time it is not, because early pricing is set against where the developer hopes the market will be, not where it is.
My rule with the 54 paper projects in this file is simple. I will show a client an unpermitted project, and I will tell them exactly which stage it is at and what still has to happen. What I will not do is let them compare its price to a permitted tower as if the two carry the same risk. They do not, and the gap in this file is not small: 34 projects are legally cleared to rise and 54 are not.
- Ask for the permit number, not the timeline. A timeline is marketing. A permit number is a public record you can verify yourself.
- Read the outside date in the contract. The marketed delivery year is not the date that binds the developer.
- Weigh your competition by stage, not by count. The 34 permitted projects are what will actually be on the market with you.
- Watch the county, not just the neighborhood. Broward projects average 746 units, so a single Broward start changes local supply far more than a Miami-Dade one.

Methodology, Scope and What This Cannot Tell You
This report reads the LuxuryDade South Florida development tracking file as of September 26, 2026. That file holds 102 entries. Eleven of them carry no dated published source yet and are excluded from every figure on this page, which leaves the 91 projects reported here. Nothing is estimated, modelled or inferred: a project appears only when a named publication or a developer's own site has reported it with a date.
Every figure on this page is produced by one script that reads that file and nothing else, so the stage table, the county table, the citation table and the register above cannot disagree with each other. The register section lists all 91 rows with the dated source behind each stage assignment, and the same rows are published as a CSV.
Stage is recorded from the most recent dated report for each project and follows the definitions in the table above. Unit counts are the developer's or the reporting outlet's published figure. Eighteen of the 91 projects publish no unit count, so every unit total on this page describes 73 projects, not 91, and the true pipeline is larger than 31,038 units. County is assigned from the project's stated address or neighborhood.
Scope limits worth stating. This is a tracked set, not a census of every condominium project in South Florida, and it inherits the coverage priorities of the outlets it is built from. It includes rental and mixed-use projects alongside for-sale condominiums, because both compete for the same land and the same construction capacity. It does not predict which paper projects will be built, and a permit is not a guarantee of delivery, only of legal clearance to begin.
Resale market context comes from MIAMI REALTORS and RWorld August 2026 Miami-Dade statistics, the Broward release and the Palm Beach release, all published September 16, 2026 and covering August 2026, the most recent county data available at publication.
Last verified September 26, 2026. This census is rebuilt from the tracking file on the same schedule the file is reviewed, so a project that clears permitting or breaks ground moves buckets here. The next scheduled update is December 2026.
Related Resources
- Miami metro building permits 2026: the federal unit-authorization series behind this pipeline
- South Florida Development Watch: every project in this file, one card each
- Download the full 91-row stage register as CSV
- Miami Condo Delivery Calendar 2026-2030: when 47 towers finish
- Miami Months of Supply 2026: the resale half of this market
- the demand side: $3.83 billion of income moved into these three counties
- New Construction Condos Miami-Dade 2026
- How to Vet a Miami Developer Before You Sign
- What Happens If You Default on a Pre-Construction Deposit
- Miami Pre-Construction Deposit Schedule 2026
- Every Miami Luxury Building We Track